Pouring the concrete

The action of pouring fresh concrete into a formwork mould. For correct pouring, the following indications should be taken into account: - Avoid sudden quick movements. - Freefall of the pouring should not exceed 1.5 to 2 m. - Lay the concrete in layers not higher than 50 cm. - The concrete must cover all reinforcements.