The action of pouring fresh concrete into a formwork mould. For correct pouring, the following indications should be taken into account:
- Avoid sudden quick movements.
- Freefall of the pouring should not exceed 1.5 to 2 m.
- Lay the concrete in layers not higher than 50 cm.
- The concrete must cover all reinforcements.