Before the start of a work, the grid is checked.
An official minute on the grid will reflect the conformity or non-conformity of the same as regards the contractual documents of the project, with particular and express reference to the geometric characteristics of the work, to the authorisation for the occupation of the necessary land and any other point that could affect the completion of the contract.
The time of execution of the works is counted from the day after the signing of the order.